WORK COMPLETED SO FAR
Since discharging the planning conditions on 25th May 2018 the enabling works such as tree removal commenced on 10th October 2018 and demolition and piling and foundation work commenced on 1st November 2018.
Once completed, the foundations were signed off by an independent Chartered Structural Engineer on 4th February 2019
TREE REMOVAL
PARTIAL DEMOLITION OF THE EXISTING BUILDING
PILING + FOUNDATIONS
PILE + FOUNDATION DESIGN
DELIVERY OF THE PILES
PILING COMMENCES
PILING COMPLETED
GROUND BEAM FOUNDATIONS COMMENCES
PILING + FOUNDATIONS PASSED